The
US Army Corps of Engineers and private consultants working for
the Riverways Program conducted extensive hydraulic and
hydrologic evaluations of the Baker and T&H Dams to
evaluate flooding considerations. They concluded that the
Baker Dam causes increased flooding and that the
T&H Dam serves no meaningful flood control purpose. They
also concluded that removing the dams would reduce
flooding on the Lower Neponset.
The
Baker Dam is particularly problematic since floodwaters
back-up behind the dam, raising floodwater levels during major
storms and causing water to spill over onto the Neponset
Greenway bikepath, the MBTA tracks and during larger floods,
into the Milton Landing area, into the planned Baker Square
Condominium common area near the dam and, under certain
conditions, into the Baker Square parking area. Making
matters worse, these floodwaters would likely be carrying a
load of toxic river-bottom sediments.
The
Department of Conservation and Recreation completed
dam safety engineering inspection reports on the Baker and
T&H Dams - the first formal dam safety
inspections completed on these dams in more than 25 years.
Those inspection reports recommended increasing the flood
hazard classification for both dams to “significant”
because the failure of one or both of these dams would create
additional flooding and might contribute to the loss of life
as well as damage to property and infrastructure.
The
failure potential of the Baker Dam is more problematic because of its close proximity to
historic mill
buildings in the Lower Mills area and the fact that the dam is
an integral part of the foundations of two of the historic
buildings.
Since
construction of the dams was completed in the mid-1960s, there
only have been
two significant flood events on the
Neponset
River - one in 1968 and one in 1998. Each of these storms was a relatively
modest flood event, at or below the 40-year flood level as
estimated by the US Geological Survey, upstream. The Baker Dam
flooded the railroad tracks and bike path during both of these
events, with 1968 being a major overflow and 1999 a more minor
overflow. During 1968, flooding also inundated the Milton
Landing area.
The
recent dam safety inspection reports for the dams indicate
that the MA DCR, which owns
and operates the dams, has no operations manual for the dams,
no operating records, no emergency operating plans, no
emergency action plan and no design plans or hydraulic data
for either dam.
Recently
updated bathymetry data show that the flood storage capacity
of the T&H Dam is only 60 acre-feet, even using the most
optimistic assumptions. Analysis of the hydrograph by
consultants Milone
and MacBroom Inc. estimates that, at best, the T&H Dam has
the capacity to store only 0.15% of the 100-year flood volume
and reduce the peak discharge rate by approximately 0.14%. So, if the T&H Dam were completely
drained before the commencement of the storm and the gates
were raised at just the right moment to shave the peak off the
“floodwave,” it would take less than 15 minutes for the
pond to refill.
Dec.
2009